RIDOT Spokesman Charles St. Martin said crews will be working on Post Road between City Hall and West Shore Road, closing sections for drainage work this week. At the Central RI Chamber of Commerce, Director Lauren Slocum reported part of the street had been shut down for the day in front of St. Catherine’s Church. She said the drainage work, which began Monday at about 7 a.m., would continue through the week.
St. Martin said lanes throughout the Apponaug Circulator had been closed the past few weeks to allow the stamped concrete crosswalks in the roundabouts to dry without interference from passing cars.
The RIDOT also outlined the following work taking place throughout the project through May 19:
- Preparation work and placement of concrete sidewalks
Centerville Road (Route 117), east of Meadow St. to Post Rd. continues to be closed to thru traffic until the final traffic configuration is implemented. Local traffic access will be maintained to the businesses.
- Curb installation
- Utility work to overhead wires
- Preparation work and placement of concrete sidewalks
Above work anticipated Monday to Friday from 6 am to 4:30 pm – This work may require lane shifts.
![[CREDIT: Lauren Slocum] A look at the intersection of Post Road, Greenwich Avenue and Centerville Road, from the Central RI Chamber of Commerce office, this morning (May 16).](https://warwickpost.com/wp-content/uploads/2017/05/Apponaug-work-May-16.jpg)
- Decorative lighting work will continue.
- Continue drainage installation work between Music Lane and Prospect Street.
Above work anticipated Monday to Friday from 7 am to 3:30 pm with one eastbound lane (left lane) available for travel. Anticipate shoulder and parking closures during working hours.
- Manhole installation within Post Road at Music Lane anticipated for Thursday night from 8 pm to 6 am the following day. Please anticipate lane shifts.
- There will be power washing and sealing at various stamped concrete locations.
- Landscaping work will continue
Please anticipate intermittent lane closures and lane shifts from 6 am to 4:30 pm, Monday to Friday.
- Continuation of concrete crosswalk work on Gilbane Street.
- At the Gilbane St. approach (northbound) to the Centerville Rd/Toll Gate Rd roundabout, the current lane shift will remain in effect for stamped concrete crosswalk curing through Monday, May 15. As this crosswalk is being done in halves, the lane shift will switch to the other side of the roadway and last through Friday, May 19.
- The southbound entrance to Gilbane St. will be closed to traffic for concrete crosswalk work since the roadway is too narrow to shift traffic to the side while work is done. Gilbane St. south traffic will be detoured to Meadow St. from Tuesday, May 9 through Tuesday, May 16 at 8 am.
- Landscaping work will continue
- Continue placing new granite curb
- Continue preparation work and placement of concrete sidewalks
This work to take place Monday to Friday from 7 am to 3:30 pm with lane shifts in effect during working hours. One lane in each direction will remain open to traffic.
- Overhead utility relocation will continue
- Stamped colored concrete crosswalk work will begin on Wednesday, May 17 at 7 a.m.
- Left lane closures will be in affect approaching and through the roundabout in all directions. The left lane closures will remain in effect for one full week. Afterwards, the right lanes entering the roundabout will be closed for one full week. Expect delays, and seek alternate routes, if possible.
- The Right lanes approaching and through the roundabout will be closed on Post Rd (from both northbound approach and southbound approach), Post Rd. Extension, and Veterans Memorial Drive for stamped concrete crosswalk work just prior to and through the roundabout. This operation is anticipated to last through Monday, May 22. Expect delays, and seek alternate routes, if possible.
- Landscaping work will continue from 7 a.m. to 3:30 p.m., Monday to Friday.
- The traffic signal was removed at Apponaug Four Corners on 4/20/2017. Please note that Greenwich Avenue and Post Road northbound have the right-of-way. A stop sign is at the Centerville Road approach. Please use caution in the area especially when turning onto Post Road Village from Greenwich Avenue.
- Motorists are reminded to yield to traffic already in the circle as they approach each roundabout and follow signage. Additionally, motorists wishing to head east (to areas such as Post Road Extension or West Shore Road) from the Centerville Road / Toll Gate Road area (by traveling on the new Veterans Memorial Drive Extension) should remain in the lanes that head straight rather than bearing right toward Greenwich Ave.
![[CREDIT: Rob Borkowski] The intersection/roundabout at West Shore Road and Post Road, facing the Veterans Memorial Drive/Post Road Extension roundabout (#3, #7).](https://warwickpost.com/wp-content/uploads/2017/05/Apponaug-work-May10_11.jpg)
![[CREDIT: Rob Borkowski] The section of Post Road between West Shore Road and Veterans Memorial Drive.](https://warwickpost.com/wp-content/uploads/2017/05/Apponaug-work-May10_10.jpg)
![[CREDIT: Rob Borkowski]](https://warwickpost.com/wp-content/uploads/2017/05/Apponaug-work-May10_12.jpg)
![[CREDIT: Rob Borkowski] A view of the sawtooth building seen from Burger King on Centerville Road.](https://warwickpost.com/wp-content/uploads/2017/05/Apponaug-work-May10_6.jpg)
![[CREDIT: Rob Borkowski] The bridge over the Apponaug River.](https://warwickpost.com/wp-content/uploads/2017/05/Apponaug-work-May10_4.jpg)
This is a test
Comments are closed.