Apponaug Project: Sidewalks, River Work, Lane Closures

Warwick,RI – The Apponaug Circulator Project, at least four months ahead of schedule thanks to a fortuitous opportunity to install new water pipes under Post Road early, is beginning to show hints of its ultimate shape at the east and west ends of construction.

We’ve collected a gallery of views of the work from Monday, Oct. 7, along with the latest from the RIDOT about ongoing lane closures and a few notes on where current work on  the project is focused:
Overnight Work
 
RIDOT will have one lane closed on Route 1 (Post Road) North, from Centerville Road to West Shore Road, Sunday-Thursday nights from 9 p.m. to 6 a.m. the following day as the water main is replaced.
One lane will also be closed on Centerville Road and one on Toll Gate Road, Monday-Thursday nights from 7 p.m. to 5 a.m. the following day to allow for installation of new drainage and traffic signal systems at the intersection of Diamond Hill and Centerville Roads.
 
Ongoing Construction
 
Two lanes will remain closed on Route 1 (Post Road), from West Shore Road to Veterans Memorial Drive, weekdays from 6 a.m. to 3:30 p.m. Crews will continue preparing the areas behind the sidewalks and driveways for walkways, parking lots and landscaping. As the contractor continues to reconstruct the Post Road Extension,  one lane will be closed from Route 1 (Veterans Memorial Drive) South, from Route 1 at the Post Road Extension to Route 5 (Greenwich Ave.), during the same time period.
On Rte. 5 (Greenwich Avenue), from Veterans Memorial Drive to Centerville Road, RIDOT will close one lane for new utility pole installation weekdays from 7 a.m. to 3:30 p.m.
Ongoing activities at the former mill site that do not involve lane closures include the excavation and embankment work, installation of a new drainage system, and the construction of the new Apponaug River upper dam structure.
Update from Mayor Avedisian’s office

Apponaug Circulator Project Weekly Update: 10.5.15 – 10.10.15
This week’s progress included:

Post Road – West Shore Road to Veterans Memorial Drive:
• Continued placing asphalt behind sidewalks and driveways.
• Placing asphalt base course on Sidestreets.
• Continue installation of new highway lighting.

Veterans Memorial Drive –Post Road to Greenwich Ave.:
• Continued reconstruction of new Post Road Airport Extension: Pavement widening, Paving & Highway Lighting.

Greenwich Avenue – Veterans Memorial to Centerville / Post Rd:
• Kettle Street was permanently closed to thru traffic on August 24th. Motorists must use Tollgate Road / Gilbert Street to access Tanner Avenue and Warwick F.O.P.

Post Road (Village) – Centerville Road Intersection:
• Continued Night-time operation for removal of old water main and installation of new main in same trench.
• Installing water service pipes, in preparation for pressure testing and chlorinating.
• Water Main installation is approximately 65% Complete.

Centerville Road – Diamond Hill Road to Tollgate Road:
• Completed drainage system on Centerville Road between Drum Rock & Diamond Hill Road.
• Relocating fire hydrant at Tollgate / Centerville Intersection.

Veterans Memorial Drive Extension (Former Mill Site):
• Continued excavation/embankment operations for new roadway.
• Continued installing new drainage system.
• Continued Construction of Apponaug River Upper Dam Structure.

Rob Borkowski
Author: Rob Borkowski

Rob has worked as reporter and editor for several publications, including The Kent County Daily Times and Coventry Courier, before working for Gatehouse in MA then moving home with Patch Media. Now he's publisher and editor of WarwickPost.com. Contact him at [email protected] with tips, press releases, advertising inquiries, and concerns.