Posted on

Apponaug Traffic Update, March 30 through April 4

Works continues this week at the site of the Warwick water tower and other locations in Apponaug.
Works continues this week at the site of the Warwick water tower and other locations in Apponaug.

Warwick, RI — The thawing of winter snows brings with it a resumption of construction and other work on the $29.9 million Apponaug Circulator Project that kicked off last fall and is expected to wrap up in 2017.

According to the Rhode Island Department of Transportation, the new roundabout at Centerville and Toll Gate Roads is next on the schedule for completion, while the most visible change in the Apponaug landscape — the removal of the water tower — is scheduled for May.

Here’s the schedule of planned work for the area for March 30 through April 4, 2015, weather permitting, as reported on the City of Warwick Apponaug Bypass web page:

Post Road – West Shore Road to Veterans Memorial Drive:

  • National Grid is scheduled to continue installation of overhead electric wires.
  • A new drainage system installation will continue at West Shore and Post Roads.
  • Construction of a new retaining wall adjacent to Shippee Ave. is also scheduled.
  • Two travel lanes will be open during the construction schedule, from 7 a.m. to 3:30 p.m.

Veterans Memorial Drive – Post Road to Greenwich Avenue:

  • National Grid is scheduled to continue installation of utility poles.
  • Three travel lanes will be open from 8 a.m. to 3:30 p.m., the scheduled construction times.

Centerville Road [Rte. 117] – Diamond Hill Road to Tollgate Road:

  • Installation of new drainage  is planned at the Tollgate/Centerville Road intersection.
  • Cox Communications and Verizon are scheduled to continue relocation of overhead wires.

Veterans Memorial Drive Extension (Former Mill Site):

  • Removal and disposal of abandoned facilities within the former Mill Site will continue, with no effect on traffic.

Greenwich Avenue – Veterans Memorial Drive to Centerville Road:

  • A planned water main installation is scheduled to begin the second week of April.
Joe Hutnak - editorjoe.warwick@gmail.com
Author: Joe Hutnak - [email protected]

Co-Founder and Editor-at-Large of Warwick Post. For Warwick Post-related inquiries or communications, email [email protected]

This is a test