RIDOT: East Avenue Lane Shifts Start Sept. 19

[CREDIT:RIDOT] Route 113 at Midland Commons Looking East on East Avenue, toward the East Avenue Bridge over Rte. 95 north and south. To the left is the Midland Mall. Night Rte. 95 Closures and Rte. 295 closures begin July 17.

[CREDIT:RIDOT] Route 113 at Midland Commons Looking East on East Avenue, toward the East Avenue Bridge over Rte. 95 north and south. To the left is the Midland Mall. Night Rte. 95 Closures and Rte. 295 closures begin July 17.
[CREDIT:RIDOT] Route 113 at Midland Commons Looking East on East Avenue, toward the East Avenue Bridge over Rte. 95 north and south. To the left is the Midland Mall. RIDOT starts East Avenue Lane Shifts for bridge demolition Friday, Sept. 19.
WARWICK, RI —Rhode Island Department of Transportation (RIDOT) will begin (Rte. 113) East Avenue lane shifts where it passes over I-95 and I-295 in Warwick.

The shift, part of RIDOT’s ongoing  $102.4 million Warwick Corridor Project, will be done in stages, but the current traffic pattern of one lane in each direction will remain in place through the rest of the year, according to the agency.

RIDOT is finishing the first phase of work, which involved demolition and replacement of three bridges that carried westbound travel over these bridges. Prior to starting the next phase of work, RIDOT will shift traffic onto these newly built bridges over the next two weeks. The schedule is as follows:

September East Avenue Lane Shifts

  • Sept. 19: The westbound lane will be shifted to the right, onto the newly built side of the bridges that pass over I-95. The lane will then shift to the left where the road passes over I-295.
  • Sept. 26: Both westbound and eastbound lanes will be fully shifted onto the newly built bridges.

All ramps and exits will remain open, with the exception of Rte. 113 East to I-95 North. That ramp was closed in early May and it will remain closed for the rest of the year.

Highway Closures for Bridge Demolition to be Announced

Later in the fall, RIDOT will conduct a series of overnight highway closures for I-95 and I-295 for bridge demolition and the setting of new steel beams, as it did earlier this summer. These closures will be announced well in advance.

The bridge replacements are part of the new $102.4 million Warwick Corridor Project. In addition to the bridge work, RIDOT will improve several other important corridors and intersections, with paving, sidewalk work, ADA accessibility, new traffic signal upgrades, and new pedestrian crossing and other safety features. Specifically, RIDOT will pave sections of East Avenue, Route 2 (Bald Hill Road), Main Avenue, West Shore Road and Post Road. More information on this project is available at www.ridot.net/WarwickCorridor.

Rob Borkowski
Author: Rob Borkowski

Rob has worked as reporter and editor for several publications, including The Kent County Daily Times and Coventry Courier, before working for Gatehouse in MA then moving home with Patch Media. Now he's publisher and editor of WarwickPost.com. Contact him at editor@warwickpost.com with tips, press releases, advertising inquiries, and concerns.